Housing Estate in the village of Cumrew, Cumbria (August 2005)
| Design Data | Plant Equipment | |
||
| Daily flow (m3/day): | 11.6 | EnSo plant: | Ocean 75/4 |
|
| BOD load (kg/day): | 3.5 |
Other: | none |
|
| Ammonia load (kg/day): | 0.5 | |||
| Effluent target: |
20:30:20 | |||
This village was not served by mains drainage and individual houses used private septic tanks and drainage fields to dispose of their sewage.
A new small housing development on the edge of the village required both primary and secondary treatment to comply with Environment Agency discharge consent conditions and it was decided to install a larger process treatment plant to allow other dwellings within the village to join the new works. Treated effluent will discharge through a sub-surface irrigation field adjacent to the treatment works.
EnSo International Ltd, together with Millennium Companies Ltd and Waitings Drainage & Pipeline Contractors, recently completed the installation and commissioning of a new wastewater treatment plant for this site.